Projektudviklingsmateriale — F25
Source: 62410 CDIO Projekt F25 Google Drive folder. The most relevant source for L1 is Aflevering 1 — Projektplan / Project Scope / Prototype design and the accompanying planning material.
Relevant for IT3E26
The F25 assignment asks students to submit a short project plan containing:
- a Project Scope Statement
- an overall project description and project goal
- identified key stakeholders and their needs
- communication requirements: when, how often and to whom
- an initial project plan with milestones
- a first prototype or design sketch
- a group contract
The assignment also asks students to identify a project leader, break work into manageable tasks, estimate time, assign responsibilities and record dependencies. These are useful later project-work practices, but should not all be taught in the first lesson.
Adaptation for E26 L2 and L4
L1 remains a pure HTML introduction. The relevant project method starts in L2 with scope definition, not a complete project management course. Groups should answer:
- What problem are we trying to solve?
- Who is the target user or stakeholder?
- What is the main goal of the system?
- What is explicitly inside the scope?
- What is explicitly outside the scope?
- What must the first prototype help us learn?
The output can be a short scope statement and a first prototype brief. This supports D1, which is a clickable frontend mockup without a backend.
Delayed material
- Detailed Gantt planning and hour accounting: introduce in L4, after the scope boundaries are clear.
- Risk analysis, communication and group contract: introduce in L6, when the groups have a concrete project to manage.
- Detailed progress tracking: use as the project develops and revisit in the status work after each milestone.
- UML and sequence diagrams: assume the prerequisite knowledge and use only when needed by the project; do not make them a dedicated L1 topic.
The original F25 assignment also contains an ethics section and a robotics specific prototype description. These should not be copied directly into IT3E26; adapt them to digital systems, health technology, privacy and the selected project case.